Klaipedos

klaipedods

 

Project Name : Reloading Station of Klaipeda

Country : Lithuania

Project Location : Klaipeda

Name of Client : Klaipedos – NAFTA

Start Date : December 2014

Completion Date : August 2015

Name of Associated Firm : Baltic-Engineer

 

Project description

Implementation of LNG Reloading Station within the existing Oil Terminal located in KLAIPEDA – LITHUANIA;

The Project consist in:

  • LNG Unloading facilities :            

     

    • LNG Carriers from 1 400 m3 to 25 000 m3 – Unloading flow of 1 000 m3/h.           
    •   LNG will come from FSRU "Independance" located nearby.
  • ‚ÄčLNG Storage :      

Horizontal pressurized tanks of 1 000 m3 storage capacity each

  • Stage 1 : 3 units
  • Stage 2 : 2 additional (5 in total)
  • Stage 3 : 1 additional (6 in total)
  • Stage 4 : 4 additional (10 in total)
  • LNG Bunkering :  

     

    • Bunkering of LNG at a maximum flowrate of 500 m3/h for oil tanker (1 000 m3) or ferries (500 m3)
  • LNG Truck Loading: 

Loading of LNG in Trucks (50 m3 – 7 barg) up to a maximum flowrate of 100 m3/h      

  • Stage 1 : 3 Truck Loading Bays
  • Stage 3 : 2 additional (5 in total)
  • Supply Fuel Gas for Oil Terminal Boiler using Ambient Air Vaporiser and Electric Heater (100 Nm3/h to 6 000 Nm3/h)

 

Scope of work

  • Task 1 – Technological Design Concept Study
  • Task 2 – FEED and QRA
  • Task 3 – EIA and Correction of Detailed Plan
  • Task 4 – Reimbursable part if necessary